PARASOL ELITE POWER · MERCED COUNTY, CALIFORNIA

Sandy Mush Interactive Campus Map

Explore the approximately 75-acre parcel as seven full-width development blocks, numbered from Sandy Mush Road toward the rear of the property. One complete 10 MW AIDC block—containing two internal 5 MW redundant paths—occupies the exact 10.00-acre Block 3, immediately north of the retired biomass plant in Blocks 1–2. Supporting equipment is arranged to the left and right of the AIDC, with the Sandy Mush Road service route along its east side. A future second 10 MW phase will reuse the cleared biomass area after demolition.

Technical feasibility study ↗Parasol Elite Power · v1.0 · October 10, 2026
10 MW Phase 1 IT load10.00 acres complete Phase 1 system7 blocks approximately 75 acresFebruary 28, 2027 projected Phase 1 completion / COD
INTERACTIVE SITE PLAN

Select an asset or street view

Focused conceptual site plan of the Sandy Mush Phase I AIDC campus

▣ Street view Phase 1 places the complete 10 MW power, compute, cooling, water and communications system inside full-width Block 3—approximately 1,056 × 412.5 ft, or exactly 10.00 acres. The rendering shows one 10 MW AIDC block; Path A and Path B are internal redundant sections, not separate AIDC blocks. Supporting equipment flanks the AIDC to the west and east, and the access road runs beside it. The biomass plant occupies most of Blocks 1–2 and has been out of operation for approximately five years; no feedstock or active operations are shown. The agricultural center is located in the designated east-side area of Block 2. The existing Sandy Mush Road access remains in place and connects to Block 3 along the owner-designated internal road. Both 800G fiber routes follow the west side of Highway 59 and separate into northbound Route A and southbound Route B. The fiber alignment is displayed in the All Systems and Fiber views only. A landscaped berm surrounds the full property. Blocks 1–2 are reserved for the future second 10 MW phase after demolition.

PRELIMINARY PROJECT BUILDER

Build a preliminary project around your power source and available space

Set the project objective, generate a starting configuration, then adjust individual quantities. Results are conceptual screening values—not a quote, permit design, reliability certification or final engineering package.

Project inputs

Installed source capacity48.1–48.3 MWSolar: 4.09–4.34 MWdc
Battery capacity40.12 MW80.24 MWh
Cooling basis24 MWth
Gross planning area10.00 acres0.00 acres remaining
AIDC canopy basis2 × 220 × 150 ft
4 × 8 ft panels1,98063,360 sq ft panel area
Added AIDC solar1.089–1.337 MWdc550–675 W per panel
Total planned solar4.089–4.337 MWdc3.00 MWdc existing plan + AIDC canopy
Parasol system componentPlanning unitQty.Equipment area
7 MW Pyrolysis Module7 MW0.63 ac
2 MW NG Generator2 MW0.92 ac
5.015 MWh BESS Container2.5075 MW / 5.015 MWh0.56 ac
Compact Solar / Auxiliary Block1 MWdc0.25 ac
AIDC Solar Canopy Block1 MWdc0.04 ac
Compact Chiller Module2 MWth planning basis0.18 ac
Compact Heat-Rejection Module2 MWth planning basis0.14 ac
Compact Modular AIDC Block5 MW IT1.52 ac

Solar capacity is nameplate DC capacity. The 1,980-panel Sandy Mush reference is a maximum rectangular packing basis using the stated 4 × 8 ft module size; final capacity may be lower after structural bays, wind design, setbacks, maintenance clearances, fire access, shading, wiring and electrical conversion are engineered. Solar is not credited as deterministic Tier IV capacity.

The Sandy Mush Phase 1 reference is fixed in full-width Block 3 at approximately 1,056 × 412.5 ft—435,600 sq ft, or exactly 10.00 acres—including the compact equipment arrangement, internal roads, fire access, service clearances and shared infrastructure. Other generated configurations use the greater of the equipment-plus-campus allowance or one acre per target MW. Final fit remains subject to vendor general arrangements, survey, fire review and licensed engineering.

HOW THE CAMPUS WORKS

Four coordinated layers, one behind-the-meter platform

01

Produce & recover

Integrated pyrolysis converts biomass into power, biochar and fertilizer while controlling the remaining emissions stream.

02

Collect & protect

Every generation source feeds the independent 15 MW / 30 MWh BESS A and/or BESS B paths. The batteries stabilize, protect and distribute all critical power.

03

Power compute

BESS A supplies only AIDC Path A and BESS B supplies only AIDC Path B. No primary or backup generator bypasses the batteries to reach compute.

04

Connect & reinvest

AT&T and VAST provide carrier-diverse 800G service; project revenue supports Merced manufacturing, education and agricultural R&D.

PHASE 1 PROJECT REFERENCE

Projected completion: February 28, 2027

The projected completion and commercial-operation date remains a management target and is subject to permits, early-work authority, equipment releases, financing, site mobilization, commissioning and the conditions identified in the technical feasibility study.

Open technical feasibility study (PDF) ↗